Drivers warned over multiple roadworks across Northampton

Drivers in Northampton are being warned to prepare for a series of temporary road closures and restrictions across the town over the coming weeks.

West Northamptonshire Council has announced a string of temporary traffic regulation orders affecting residential streets, key routes and including a town centre bus lane, with works ranging from new tactile crossings to water main repairs.

One of the first closures will affect Donellan Green, where traffic will be prohibited from Barley Hill Road for 100 metres from March 4, 2026. The restriction is needed to allow the safe installation of new tactile crossings and is expected to last up to three days. A diversion will be in place via Teeside, Duckwell Dell and Barley Hill Road.

Melville Street will also close between Talbot Road and Artizan Road from March 3, 2026 for up to three days to allow work on a water main. Drivers will be diverted via Artizan Road, Henry Street, Kettering Road and Talbot Road.

Road closures across Northampton and beyond have been announced. Library picture. Getty Imagesplaceholder image
Road closures across Northampton and beyond have been announced. Library picture. Getty Images

In the town centre, part of Upper Cross Street will shut for one day on March 5, 2026 between Upper Bath Street and Crispin Street to enable carriageway repairs. A diversion route will take traffic along Scarletwell Street, St Andrews Road, St Peters Way, Horsemarket, St Marys Street and Castle Street.

Elsewhere in Northampton, Victoria Road will close from its junction with Wellingborough Road for up to three days from February 16, 2026 while repairs are carried out to a fire hydrant. Traffic will be diverted via St Edmunds Road.

Fawsley Road, between Queen Eleanor Road and Hereward Road, is also set to close for up to three days from February 18, 2026 to allow pipe repairs to take place.

A section of Birds Hill Walk footpath, to the rear of the school, will be closed for up to seven days from February 16, 2026 during new water main works, with pedestrians diverted via Billing Brook Road.

Meanwhile, the bus lane on St James Road will be temporarily closed for two days from February 17, 2026 between the exit of the bus stop by Halford Autocare and the pedestrian crossing to allow telecom works to be completed.

Beyond Northampton, further temporary closures are planned across West Northamptonshire.

Church View in Brafield on the Green will shut for one day from March 2, 2026 for telecom works, while Sulgrave Road in Helmdon will close for one day from March 3, 2026 for drainage works.

Blisworth Arm in Blisworth is scheduled to close for up to three days from March 3, 2026 for a new water connection, and High Street in Scaldwell will be shut for up to six days from February 16, 2026 during new electric connection works.

Middleton Road in Chacombe will close for one day from February 17, 2026 for pipe repairs, and Eastcote Road in Gayton will shut for one day from February 18, 2026 for overhead telecom works.

All of the orders will remain legally in force for up to 18 months, although the restrictions will only apply when signs are displayed and are expected to last for the shorter durations outlined.

News you can trust since 1931
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice