Busy country road near Northampton to remain closed longer as reopening delayed again
A busy country road near Northampton is set to remain closed for longer as its reopening has been delayed again.
The reopening of Nobottle Road also known as Roman Road between Duston and Harpole could now be delayed until ‘spring 2027’ following major problems with an Anglian Water main on the route.
The site was previously signposted for reopening in February 2027, but West Northamptonshire Council now says the earliest likely completion is spring next year.
The council said: “This developer-led scheme on Roman Road has been significantly delayed due to the unexpected failure and required replacement of around 1km of an Anglian Water main, which could not be worked around due to safety restrictions.


“The water main replacement work is now nearing completion, and Anglian Water will need to test the system to ensure it is working before the developer can restart the roadworks.
“Based on current estimates, the earliest likely completion of the project is now expected to be spring next year.”
The road has been closed since January 2026 as part of works linked to the 450-home Roman Fields development. It was originally due to reopen in September this year.
An Anglian Water spokesman said: “Following damage to one of our water mains by contractors working on the Roman Road scheme earlier this year, our teams carried out emergency repairs to restore supplies to around 2,700 customers who were affected by low pressure or interruptions to their water supply.
“The water main was subsequently damaged again, resulting in further repairs being required. As investigations progressed, it became clear that the planned roadworks and groundworks would take place in close proximity to our infrastructure. To protect a critical water supply asset and ensure the safety of both the public and those working on site, it was agreed that the water main would be repositioned before the wider road improvement works could continue.
“We have worked as quickly as possible to complete this work and the water main replacement is now nearing completion. Once final works and testing have been carried out, the developer will be able to resume the road improvement scheme.
“We recognise the frustration caused by delays to the project and continue to work closely with the developer and local partners to support the safe completion of the remaining works, whilst protecting water supplies for customers in the area.”
Davidsons Homes previously said: “The delay to the Nobottle Road works relates solely to an existing water main within the road corridor. During the works, the main, which is constructed from asbestos cement, began failing in multiple locations despite not being struck by our works.
“Following this, Anglian Water instructed that works in the vicinity of the main cease while a diversion solution was agreed. This has resulted in the delays currently being experienced.”
However, the developer later withdrew that statement and replaced it with the following:
“The delay to the Roman Road works is due to the need to divert an existing water main.
“The current programme indicates the road will reopen in February 2027, although we will continue working to improve this where possible.
“The southern arm of the new roundabout is currently expected to open in September 2026, allowing vehicles to turn left out of Harpole only.”
Harpole Parish Council said it recently met with the developer to discuss the revised programme.
Harpole Parish Council said: “They have suggested that they will be able to open up access on the roundabout in early September and will be working to be able to have this open as an entrance /exit towards Daventry for Scarecrow weekend. If we would like this could then remain open for residents to use. The road towards Duston will still be closed until the works are completed.”